Phase 1 roadmap: russetleaf.dev

The milestones for building Phase 1, with target dates, and the actual dates once each is reached. The steps, tiers and estimates come from the plan's progress checklist; day-to-day work is tracked as GitHub Issues (one per step) grouped into these milestones, on a public GitHub Projects board.

Assumptions (baseline of 2026-11-02)

  • Start: Monday, November 2, 2026.
  • Pace: about 60 hours a week, worked as 10 hours a day, six days a week, with Saturdays off.
  • Order: the Core tier first (in plan order), then the Differentiators, then the Staff and Stretch steps, as the plan recommends.
  • Estimates: the plan's focused-hour ranges (expect ±50%). Target is the date at the midpoint of the estimates; latest is the date at the high end.
  • Not included: holidays (Thanksgiving, late December), days lost to waiting (box 3's delivery, AWS approvals, DNS), and the drop in pace that long stretches of 10-hour days usually bring. Plan around the latest dates.

Milestones

Milestone Steps Est. hours Target Latest Actual Actual hours
M1 Foundations 0.1–1.1 11–21 Tue, Nov 3, 2026 Wed, Nov 4, 2026
M2 Cluster and AWS foundations 2.0–2.4 36–57 Mon, Nov 9, 2026 Tue, Nov 10, 2026
M3 GitOps and platform services 3.1–4.7 41–67 Sun, Nov 15, 2026 Wed, Nov 18, 2026
M4 WordPress live with staging and promotion 5.1–5.7, 5.10, 5.12 54–91 Mon, Nov 23, 2026 Sun, Nov 29, 2026
M5 Core tier complete and published 6.1, 6.3, 9.2 27–39 Fri, Nov 27, 2026 Thu, Dec 3, 2026
M6 Senior tier: operations evidence 2.5, 5.8, 5.9, 5.11, 6.2, 6.4, 6.5, 7.1–7.6, 7.8–7.12, 9.1 72–127 Wed, Dec 9, 2026 Fri, Dec 18, 2026
M7 Staff tier and Phase 1 complete 7.7, 8.1–8.9 89–144 Tue, Dec 22, 2026 Mon, Jan 4, 2027
Total 330–546

What each milestone shows when it's done:

  • M1: accounts, tools, budget alert, network segmentation, decisions recorded, the repos public with their CI guardrails.
  • M2: the AWS Organization with its security services, the three-node Talos cluster with Cilium, the home AWS and Cloudflare resources, and the Terraform pipeline.
  • M3: Argo CD managing everything; storage, secrets and certificates, ingress through the tunnel, monitoring and alerting, MariaDB and Valkey, logging, and OIDC sign-in.
  • M4: russetleaf.dev live on the custom image and theme, with ci tests, on-demand staging, promotion and the privacy basics.
  • M5: Kyverno and network policies enforced, the docs polished, and the project published as a finished Core tier. First portfolio milestone.
  • M6: progressive delivery, sandboxing, runtime security, cost and tracing, keyless AWS access, and the rollback, node-failure and disaster drills.
  • M7: SLOs and error budgets, DORA metrics, Backstage and a second service, the threat model and control matrix, chaos and postmortems, strategy documents, fleet management, and public writing.

Tracking and reporting

  • Issues: one per step, created from the plan by tools/plan_to_issues.py (see its usage notes), labeled by tier and stage, in the milestone above, with the step's substeps as a checklist and its test as acceptance criteria.
  • Step specs: before starting a step, write its spec with Claude from ../specs/TEMPLATE.md; the pull request links the issue and the spec.
  • Actuals: record actual hours per step in the plan's checklist, and fill in this table's Actual columns when a milestone closes.
  • Milestone retro: when a milestone closes, add a short note to the plan's decision log: estimated vs actual hours, what took longer and why, and what changes for the next milestone.
  • Re-baselining: if a milestone finishes more than a week late, re-plan the remaining dates here (keep the original baseline in Git history and say so in the decision log) rather than letting the table go stale.